Started on front and back walls after we got back from vacation, first week if October but was shorted 10 sheets of metal so put up what we could then moved to roof which we were able to get done in 2 days. Being short the other metal had to wait 2 weeks for metal to come in and finished rest of walls today. Now just have to finish backfilling inside and out, stone the floor, finish wiring and wait for garage door to be installed. Hopefully next week or two will be completely done. Oh ya and hit the brushing and mowing of the trails also.
Still have some work left to do on the shed but it’s usable for the winter. Had garage door installed on Monday and finished wiring lights when they were installing door. Also loaded it all before rain and snow came.